Additional Works on Line 353 in the Olsztyn Area

Additional works on railway line no. 353, which Trakcja PRKiI S.A. will carry out under a supplementary task, are worth more than PLN 7 million.

The annex provides for the preparation of design documentation and the replacement of the track superstructure over a combined section of approx. 5 km and at 4 level crossings. 

Completion of the works has been set for April 2018.