Additional Works on Line 201

The additional works on railway line no. 201, to be carried out by Trakcja PRKiI S.A. under a supplementary task, are worth more than PLN 25 million.

Under the annex, the overhead contact line will be comprehensively rebuilt on two sections with a combined length of 15 km. In addition, the track superstructure will be replaced and a level crossing will be repaired. The works will be carried out on the Nowa Wieś Wielka – Maksymilianowo section.

The deadline for completion of the works has been set for 30 September 2017.