We Are Designing for PGE
Trakcja PRKiI will prepare for PGE Dystrybucja S.A. complete design and cost estimate documentation for replacing almost 16 km of overhead low- and medium-voltage power lines with underground cable. The design will also include the construction of pole-mounted and indoor transformer stations in the localities of Radzic Stary and Radzic Nowy in the Lublin Voivodeship.
In future, the planned investment will contribute to increasing the region’s energy security in terms of a stable supply of electricity and will create conditions for connecting new customers and renewable energy installations.
Completion of the design work is planned for May 2022, and the value of the contract is almost PLN 0.5 million net.
Informacje dla mediów
Robert Kuczyński
dyrektor ds. komunikacji
r.kuczynski@grupatrakcja.com