23/02/2024
Sewerage Works Related to the Reconstruction of the K-3 Sewer on Railway Line No. 7
Execution of construction works related to the reconstruction of the sanitary sewer along railway line No. 7 as part of the project entitled: “Works on railway line No. 7 Warszawa Wschodnia Osobowa – Dorohusk on the Warszawa – Otwock – Dęblin – Lublin section, Stage IIa”.
Client:
PKP Polskie Kolejowe S.A.
Implementation period:
8 January 2024 –
Value of works:
PLN 17.8 million net
Scope of works:
Trakcja will build, using a trenchless method, a sanitary sewer more than 900 m long using microtunnelling with a diameter of 800 mm, and will install more than 24 polymer concrete chambers and manholes