Improving Service Conditions and Development of Starachowice Special Economic Zone S.A., Including Through the Construction of a Grade-Separated Road Overpass over Railway Line No. 25 in Starachowice

Improving the service conditions and development of SSE Starachowice S.A., including through the construction of a grade-separated road overpass over railway line No. 25 in Starachowice.

Client:

County Roads Authority in Starachowice (Zarząd Dróg Powiatowych w Starachowicach)

Implementation period:

16 May 2023 – August 2025

Value of works:

PLN 91.8 million gross

Promotional material:

Scope of works:

The road overpass was designed in steel-arch technology, the structure provides optimal usage parameters, and illumination of the overpass was additionally installed, with the possibility of setting any colours and lighting scenes.

During the construction of the overpass, the Father Jerzy Popiełuszko roundabout was rebuilt, which is the first turbo roundabout in Starachowice. Vehicle traffic has become more orderly, smoother and safer. At the same time, all accompanying infrastructure was rebuilt, from underground networks to the modernisation of surrounding streets.

Road Overpass – Radomska Street

  • Type: single-carriageway overpass above railway tracks.
  • Length: 67.00 m
  • Width: 16.65 m
  • Location: above the railway lines running from Skarżysko-Kamienna to Sandomierz, line No. 25
  • Road layout:
    • Two carriageways, each with one traffic lane 3.5 m wide and edge strips of 0.5 m on both sides (total width 8.0 m)
    • Cycle path 2.4 m wide
    • Pavement 2.25 m wide

(visualisations: @Fotgraf3D, photo: Maciej Myszka )