Podłęże – Bochnia

Design and execution of construction works on the Kraków – Medyka – state border railway line, on the Podłęże – Bochnia section at km 16.000 – 39.000; Tender 1.1

Client:

PKP Polskie Linie Kolejowe S.A. - Head Office

Implementation period:

11/2/2010 - 10/7/2016

Value of works:

PLN 642.0 million

Scope of works:

The scope of works includes the modernisation of a double-track railway line over a length of 23 km:

  • design documentation,
  • track layout and track drainage,
  • overhead contact line,
  • traffic control and diagnostics equipment,
  • telecommunications networks and equipment,
  • non-traction power networks and equipment,
  • engineering structures: culverts – 40 pcs, viaducts – 15 pcs, bridges – 2 pcs,
  • level crossings and access roads,
  • buildings, platforms, small architecture and sanitary networks.