31/05/2011

LCS Malbork

Modernisation of line No. 9 on the section from km 236.920 to km 287.700 within the area of the Local Control Centre based in Malbork (LCS Malbork)

Client:

PKP Polskie Linie Kolejowe S.A.-Head Office

Implementation period:

5/27/2011 - 7/31/2015

Value of works:

PLN 889.0 million

Scope of works:

The scope of works includes the modernisation of a double-track railway line over a length of 51 km, including:

  • modernisation of track layouts together with modernisation of the subgrade, drainage and trackside infrastructure and platforms,
  • overhead contact line,
  • railway traffic control equipment,
  • telecommunications equipment and networks together with passenger information,
  • non-traction power supply line,
  • medium- and low-voltage railway power engineering networks and equipment,
  • construction of new grade-separated crossings: wildlife crossing, railway viaducts – 8 pcs, road viaducts – 7 pcs, pedestrian underpass,
  • closure of level crossings together with construction of diversion roads,
  • maintenance buildings,
  • environmental protection facilities.