Kurs otwarcia: TRK 3.4500 Kurs bieżący: TRK 3.4200 D/D-1: -0.0300 (-0.87%) Więcej
PL | EN
 
22/02/2024

Renovation of Traction Substation A9 Racławicka

Carrying out modernisation of the traction and power substation involving replacement of DC equipment at station A9 Racławicka of Metro Line I in Warsaw.

Zamawiający:

Capital City of Warsaw

Okres realizacji:

19 February 2024

Wartość robót:

PLN 4.9 million gross

Zakres robót:

The scope of work covered by the contract provides for replacement of RPS switchgear (10 bays), SKP and switchgear of our own production: RST (traction network switchgear) – 8 units, earthing disconnector cabinets (SOU) – 4 units and SZW – 2 units.