22/02/2024
Renovation of Traction Substation A9 Racławicka
Carrying out modernisation of the traction and power substation involving replacement of DC equipment at station A9 Racławicka of Metro Line I in Warsaw.
Zamawiający:
Capital City of Warsaw
Okres realizacji:
19 February 2024
Wartość robót:
PLN 4.9 million gross
Zakres robót:
The scope of work covered by the contract provides for replacement of RPS switchgear (10 bays), SKP and switchgear of our own production: RST (traction network switchgear) – 8 units, earthing disconnector cabinets (SOU) – 4 units and SZW – 2 units.