25/11/2016 16:35
Power Engineering Works in Nadarzyn
Trakcja PRKiI S.A. will carry out construction works and connect the facility to the power grid at Nadarzyn Industrial Park Sp. z.o.o. The contract signed with PGE Dystrybucja is worth PLN 750 thousand net.
The contract consists of two tasks, which will involve building a 15 kV MV cable line in Nadarzyn towards Wolica and an MV cable connection point along Aleja Katowicka.
The deadline for completion of the works has been set for April 2017.
Informacje dla mediów
Robert Kuczyński
dyrektor ds. komunikacji
r.kuczynski@grupatrakcja.com