Reconstruction of 110 kV Line in Jarosław

Almost PLN 1.5 million will be the cost of the power engineering works that Trakcja PRKiI S.A. will carry out for PGE Dystrybucja S.A. Zamość Branch.

The investment involves demolishing two single-circuit 110 kV lines and building one double-circuit line on the section from pole no. 41/6 to the existing 110/30/15 kV Jarosław substation. The works will include building 6 tubular poles, for which well foundations have been designed. The length of the new line will be about 1.1 km.

Completion of the works is planned for the end of November 2017.