Modernisation of 11 km overhead line

Works that are to be performed by Trakcja PRKiI S.A. pursuant to the contract concluded with PKP PLK S.A. will cost approximately 7 million zloty. The Contract provides for designing and performing power industry works on both tracks of the rail line section Inowrocław – Bydgoszcz Główna.

The task involves drawing up design documentation and performing a complex modernisation of the rail line section 131 Chorzów Batory – Tczew. Works will include disassembly and assembly of overhead line and accompanying infrastructure at the 11 kilometres section.

The ending date of the works was set at the end of August 2016.

 

Media Information

Robert Kuczyński

communications manager

r.kuczynski@grupatrakcja.com